{"img_type":"['Diagrams']","options":"['None of the other answers', '<image 5>', '<image 1>', '<image 2>', '<image 3>', '<image 4>']","question":"Suppose four processes, P1, P2, P3 and P4, with CPU burst times of 6, 8, 7 and 3, respectively, arrive in the order P1, P2, P3, P4 at times 0, 1, 2, and 3, respectively. If the CPU is using a preemptive shortest-job-first schedule, which Gantt chart represents the execution schedule?","subject":"Computer_Science"}