{"choices":"['$2,005,000', '$1,975,000', '$1,945,000', '1910000']","question":"Pine Co. purchased land for $450000 as a factory site. An existing building on the site was razed before construction began. Additional information is as follows: Cost of razing old building $60000 Title insurance and legal fees to purchase land $30000 Architect's fees $95000 New building construction cost $1850000 What amount should Pine capitalize as the cost of the completed factory building?","subject":"professional_accounting"}