Two power line construction routes are being considered. Route A is 15 miles long and goes around a lake. Each mile will cost 6,000tobuildand6,000 to build and 2,000 a year to maintain. At the end of fifteen years, each mile will have a salvage value of 3,000.RouteBisanunderwaterlinethatcuts5milesacrossthelake.Constructioncostswillbe3,000. Route B is an underwater line that cuts 5 miles across the lake. Construction costs will be 31,000 per mile and annual maintenance costs, 400permile.Thesalvagevalueattheendoffifteenyearswillbe400 per mile. The salvage value at the end of fifteen years will be 6,000 per mile. Assuming interest is 8% and taxes are 3% of the construction costs of each power line, compare the annual costs of Route A and Route B for the first year.
Plain-text mathematical notation (without MathML)
Two power line construction routes are being considered. Route A is 15 miles long and goes around a lake. Each mile will cost 6,000tobuildand2,000 a year to maintain. At the end of fifteen years, each mile will have a salvage value of 3,000.RouteBisanunderwaterlinethatcuts5milesacrossthelake.Constructioncostswillbe31,000 per mile and annual maintenance costs, 400permile.Thesalvagevalueattheendoffifteenyearswillbe6,000 per mile. Assuming interest is 8% and taxes are 3% of the construction costs of each power line, compare the annual costs of Route A and Route B for the first year.
Original LaTeX notation
Two power line construction routes are being considered. Route A is 15 miles long and goes around a lake. Each mile will cost $6,000 to build and $2,000 a year to maintain. At the end of fifteen years, each mile will have a salvage value of $3,000. Route B is an underwater line that cuts 5 miles across the lake. Construction costs will be $31,000 per mile and annual maintenance costs, $400 per mile. The salvage value at the end of fifteen years will be $6,000 per mile. Assuming interest is 8% and taxes are 3% of the construction costs of each power line, compare the annual costs of Route A and Route B for the first year.

category

business

options

  1. $41,558 for Route A and $23,654 for Route B
  2. $45,000 for Route A and $30,000 for Route B
  3. $100,000 for Route A and $50,000 for Route B
  4. $40,000 for Route A and $20,000 for Route B
  5. $80,000 for Route A and $40,000 for Route B
  6. $35,000 for Route A and $25,000 for Route B
  7. $70,000 for Route A and $35,000 for Route B
  8. $60,000 for Route A and $155,000 for Route B
  9. $90,000 for Route A and $155,000 for Route B
  10. $120,000 for Route A and $75,000 for Route B

src

stemez-Business

Discussion

Discussion

No discussion posts on this page yet. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.

See answer Answer published by the source

Artifacts

Code, notes and reproducible work shared by participants. Files are served from a separate origin.

No artifacts on this page yet. Share reproducible code or notes in a contribution. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.

Source and history

Official source

initial import