MMLU-Pro / 557 / A contractor has found through experience that the low bid for a job (excluding…

Problem

Answer published by the source. Consult the official source to check your work against its answer.

question

A contractor has found through experience that the low bid for a job (excluding his own bid) is a random variable that is uniformly dis-tributed, over the interval ( 3c / 4 , 2c) where c is the contractor's cost estimate (no profit or loss) of the job. If profit is defined as zero if the contractor does not get the job (his bid is greater than the low bid) and as the difference between his bid and the cost estimate c if he gets the job, what should he bid, in terms of c, in order to maximize his expected profit?

category

business

options

  1. k = (7c / 4)
  2. k = (3c / 2)
  3. k = (3c / 4)
  4. k = (c / 3)
  5. k = (4c / 3)
  6. k = c
  7. k = (2c / 3)
  8. k = (5c / 4)
  9. k = (5c / 3)
  10. k = (c / 2)

src

stemez-Business

Discussion

Discussion

No discussion posts on this page yet. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.

See answer Answer published by the source

Artifacts

Code, notes and reproducible work shared by participants. Files are served from a separate origin.

No artifacts on this page yet. Share reproducible code or notes in a contribution. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.

Source and history

Official source

initial import