Problem
Answer published by the source. Consult the official source to check your work against its answer.
question
An owner of a large, three-story office building planned to renovate the building and requested several contractors to submit bids to perform the work. One of the contractors in turn sought bids from several subcontractors to determine the overall cost of the job. An electrician submitted a bid to do the electrical work to the contractor, which the contractor used in computing the bid he sent to the owner. The contractor notified the electrician to that effect. Two weeks later, the contractor submitted his bid to the owner, in which he offered to perform the renovation work for
$75,000. The next day, the electrician notified the contractor that he was unable to perform the electrical work on the owner's project. Two days later, the owner sent the contractor a signed confirmation letter wherein she stated, "I hereby accept your offer to perform the renovation work for the quoted cost of $75,000. "Thereafter, the contractor hired another electrician to complete the electrical work at a cost of $5,000 above the first electrician's bid. The contractor explained the situation to the owner and informed her that the overall cost of the job would have to be increased to $80,000. The owner responded that she would hold the contractor to his original bid of $75,000 and would not be responsible for any additional costs. The contractor then performed the renovation work, but the owner has not yet paid him anything. In an action by the contractor against the owner for the services rendered, the contractor will probably be able to recoverPlain-text mathematical notation (without MathML)
An owner of a large, three-story office building planned to renovate the building and requested several contractors to submit bids to perform the work. One of the contractors in turn sought bids from several subcontractors to determine the overall cost of the job. An electrician submitted a bid to do the electrical work to the contractor, which the contractor used in computing the bid he sent to the owner. The contractor notified the electrician to that effect. Two weeks later, the contractor submitted his bid to the owner, in which he offered to perform the renovation work for $75,000. The next day, the electrician notified the contractor that he was unable to perform the electrical work on the owner's project. Two days later, the owner sent the contractor a signed confirmation letter wherein she stated, "I hereby accept your offer to perform the renovation work for the quoted cost of $75,000. "Thereafter, the contractor hired another electrician to complete the electrical work at a cost of $5,000 above the first electrician's bid. The contractor explained the situation to the owner and informed her that the overall cost of the job would have to be increased to $80,000. The owner responded that she would hold the contractor to his original bid of $75,000 and would not be responsible for any additional costs. The contractor then performed the renovation work, but the owner has not yet paid him anything. In an action by the contractor against the owner for the services rendered, the contractor will probably be able to recover
Original LaTeX notation
An owner of a large, three-story office building planned to renovate the building and requested several contractors to submit bids to perform the work. One of the contractors in turn sought bids from several subcontractors to determine the overall cost of the job. An electrician submitted a bid to do the electrical work to the contractor, which the contractor used in computing the bid he sent to the owner. The contractor notified the electrician to that effect. Two weeks later, the contractor submitted his bid to the owner, in which he offered to perform the renovation work for $75,000. The next day, the electrician notified the contractor that he was unable to perform the electrical work on the owner's project. Two days later, the owner sent the contractor a signed confirmation letter wherein she stated, "I hereby accept your offer to perform the renovation work for the quoted cost of $75,000. "Thereafter, the contractor hired another electrician to complete the electrical work at a cost of $5,000 above the first electrician's bid. The contractor explained the situation to the owner and informed her that the overall cost of the job would have to be increased to $80,000. The owner responded that she would hold the contractor to his original bid of $75,000 and would not be responsible for any additional costs. The contractor then performed the renovation work, but the owner has not yet paid him anything. In an action by the contractor against the owner for the services rendered, the contractor will probably be able to recover
choices
- only in quantum meruit, because of the doctrifle of commercial frustration.
- only in quantum meruit, because by demanding $80,000 the contractor, in effect, repudiated his contract with the owner.
- $75,000 only, because that was the contract price.
- $80,000, because the contractor reasonably relied to his detriment on the electrician's bid in formulating his job estimate.
subject
professional_law
Discussion
No discussion posts on this page yet. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.
See answer Answer published by the source
Artifacts
Code, notes and reproducible work shared by participants. Files are served from a separate origin.
No artifacts on this page yet. Share reproducible code or notes in a contribution. State an approach you tried, the evidence it uses, and a specific question another participant could help resolve. Use the posting template.
Source and history
initial import